Six Sigma tools explained

Six Sigma is a method for cutting defects by making a process less variable. A project runs in five phases, called DMAIC, and each phase has its own tools. This guide explains each tool and works one example through all five phases.

Matt Savas · Reviewed October 2026 · About 9 minutes

What Six Sigma is

Every process has variation. No two parts come off a machine at exactly the same size, and no two orders take exactly the same time. When the variation is large, some results fall outside what the customer will accept. Those are defects. Six Sigma finds the causes of variation and removes them.

Sigma (σ) is the Greek letter used for standard deviation, a measure of how spread out the results are. A small σ means the results sit close together. A process runs at six sigma when six standard deviations fit between its average and the nearest limit the customer sets. Such a process makes about 3.4 defects per million chances. That figure assumes the average drifts by 1.5σ over time, as most real processes do.

Six Sigma began at Motorola in 1986. General Electric adopted it in 1995 and made it widely known. Many companies now combine it with lean as Lean Six Sigma. Lean works on wait time and wasted steps. Six Sigma works on defects.

What DMAIC is

DMAIC stands for the five phases of a Six Sigma project: Define, Measure, Analyze, Improve and Control. Each phase answers one question, and each one uses what the phase before it found. A team that skips ahead usually ends up fixing the wrong thing.

The tools in each phase

  1. 1
    Define: what problem, and how big is the project?
    The team writes a project charter. It is one page with the problem, the goal, the scope, the team and the dates. A SIPOC lists the suppliers, inputs, process steps, outputs and customers on one page. It sets where the project starts and stops. The free SIPOC builder lays one out for you.
  2. 2
    Measure: how does the process run today?
    First check the gage with a Gage R&R study. Several people measure the same parts several times, and the study shows how much of the spread comes from the gage. Under 10% is good. Over 30% means you fix the gage first. Then plot the data on a control chart to see if the process is stable. A stable process can be compared with its spec using Cp and Cpk. The DPMO calculator turns the defect count into a sigma level.
  3. 3
    Analyze: what causes the defects?
    A Pareto chart sorts the defects by count, largest first, so the team works on the biggest one. A fishbone diagram lists the possible causes under six headings: people, methods, machines, materials, measurement and environment. The five whys follow one cause down to its root. The team then proves the cause: remove it and the defect stops; bring it back and the defect returns. An FMEA rates each way a step can fail for severity, how often it happens and how easily it is caught. Each is scored 1 to 10, and the product of the three ranks the risks.
  4. 4
    Improve: does the fix work?
    The team removes the proven cause. Many fixes come from lean: poka-yoke devices that stop an error, or a new standardized work sequence. When several machine settings might matter, a designed experiment changes them in a planned pattern to find which ones do. The team tries the fix on a small scale, then runs the capability study again to check the gain.
  5. 5
    Control: will the gain last?
    The control chart goes back on the process with new limits worked out from the improved data. A reaction plan says who does what when a point falls outside the limits. The new method is written down as a work instruction and taught to every shift. The process owner then takes over from the project team.

A worked example: one machining cell

A CNC cell machines aluminum housings. It makes 2,500 a month and scraps 105 of them. That is 4.2%, and it has stayed there for six months.

Define

The charter sets the goal: cut scrap from 4.2% to under 2% in 90 days. Scrap tags show that 89 of the 105 (bore undersize, surface finish and wrong depth) come from the CNC mill. The SIPOC puts the project boundary around the mill, so the team does not spend the first month mapping the whole plant.

Measure

The bore in each housing must be 20.00 mm, plus or minus 0.15 mm. Anything from 19.85 to 20.15 mm passes. The Gage R&R on the bore gage comes back at 8%, so the readings can be trusted. A control chart of the bores shows no points outside its limits. The bores average 19.94 mm with a standard deviation (σ) of 0.046 mm.

Cp compares the width of the spec with the width of the process. Cpk does the same but uses the distance from the average to the nearer limit, so it falls when the process is off center.

Cp = (20.15 − 19.85) ÷ (6 × 0.046)= 0.30 ÷ 0.276 = 1.09
Cpk = (19.94 − 19.85) ÷ (3 × 0.046)= 0.09 ÷ 0.138 = 0.65

A Cp of 1.09 says the spread would just fit inside the spec if the process were centered. A Cpk of 0.65 says it is not centered. The average sits low, and about 2.5% of bores fall below 19.85 mm. That is 63 housings a month. Most plants want a Cpk of at least 1.33.

The team checks five things on every housing: bore size, surface finish, burrs, depth and scratches. Each is a chance for a defect, so a month has 2,500 × 5 = 12,500 chances.

DPMO = 105 ÷ 12,500 × 1,000,000= 8,400

A DPMO of 8,400 is about 3.9 sigma, using the usual 1.5σ shift.

Analyze

The Pareto chart shows that one defect makes up most of the scrap. Bore undersize is 63 of the 105 scrapped housings, or 60%.

Scrapped housings by defect
One month: 105 scrapped out of 2,500 made.
Bore undersize
63
Surface finish
18
Burrs
12
Wrong depth
8
Scratches
4

The fishbone for bore undersize lists four likely causes: insert wear, coolant mix, a skipped machine warm-up and a mistyped tool offset. Operators changed the cutting insert when it looked worn. Nobody counted parts.

The team measures every bore across the life of one insert. The bores get smaller as the insert wears and drop below 19.85 mm after about 400 parts. With a new insert, they come straight back to size. Worn inserts make undersize bores and new ones don't, so the cause is proven.

The team also logs the coolant mix for two weeks. On days the mix is off, the bores spread wider. When the mix is put right, the spread narrows again.

Improve

The team makes two changes. The insert is now changed every 300 parts and the offset reset, which moves the average to 20.00 mm. A coolant mix check every shift cuts σ from 0.046 to 0.030 mm. Move each slider to apply each change.

Bore sizes against the spec
The amber areas are bores out of spec.
Average 19.940 mm
σ 0.046 mm
2.5%
Lower limit
19.85 mm
Upper limit
20.15 mm
Cp
1.09
Cpk
0.65
Bores out of spec, per million
25,204

Not capable: Cpk is under 1.00.

Centering alone raises Cpk from 0.65 to 1.09. Cutting the spread alone raises it to 1.00. Both together give 1.67, and bore scrap falls to almost zero.

The next month, the cell scraps 42 housings, all for the other four defects. That is 1.7%, under the 2% goal. DPMO falls from 8,400 to 3,360.

Control

The new control limits come from the improved process: the average of 20.00 mm, plus and minus three times σ of 0.030 mm. That puts them at 19.91 and 20.09 mm. They sit inside the spec limits, so the chart warns before any bore is scrapped.

Over one 30-hour run three weeks after the project closes, an operator skips an insert change at hour 19. The bores start to shrink.

Control chart of the bore, one bore an hour
Limits worked out after the fix and left unchanged.
20.0920.0019.9119.85Lower spec limit
Hour 1Hour 30
  • Control limits, 19.91 and 20.09 mm
  • Center line, 20.00 mm
  • Hour 25: 19.88 mm, below the lower control limit
  • Lower spec limit, 19.85 mm

At hour 25 the bore measures 19.88 mm, below the lower control limit of 19.91 mm. It is still above the 19.85 mm spec limit, so no housing is scrapped. The reaction plan tells the operator to stop, change the insert and check the parts made since hour 19. From hour 26 the bores are back near 20.00 mm.

Common mistakes

  • Measuring before checking the gage. If the gage adds a lot of spread, every chart and capability number after it is wrong.
  • Working out Cpk on an unstable process. Cpk predicts the future only when the control chart shows the process is stable. Make it stable first.
  • Mixing up control limits and spec limits. Spec limits come from the drawing or the customer. Control limits come from the process data. A point can be outside the control limits and still inside the spec.
  • Counting extra chances for defects. Adding things to check raises the opportunity count and makes the sigma level look better without fixing anything. Count only the things a customer would reject a part for.
  • Choosing the cause by vote. A cause is proven when turning it off stops the defect and turning it back on brings it back.
  • Recalculating the limits after a drift. Limits worked out from drifting data widen to fit the drift. Keep them fixed until the process is changed on purpose.

Frequently asked questions

What is DMAIC?
DMAIC is the five phases of a Six Sigma project. Define the problem, the goal and the scope. Measure how the process runs today, after checking the gage. Analyze the data until one cause is proven. Improve the process by removing that cause, and measure again. Control the process so the gain lasts after the project team moves on.
What are the main Six Sigma tools?
Define uses a project charter and a SIPOC. Measure uses a Gage R&R study, a control chart, Cp and Cpk, and DPMO with a sigma level. Analyze uses a Pareto chart, a fishbone diagram, the five whys and an FMEA. Improve often uses lean tools such as poka-yoke and standardized work, plus designed experiments. Control uses a control chart with fixed limits, a reaction plan and written work instructions.
What does 3.4 defects per million mean?
It is the defect rate of a process that runs at six sigma. Six standard deviations fit between the average and the nearest spec limit. The 3.4 figure assumes the average drifts by 1.5 standard deviations over time, which leaves 4.5 standard deviations to the limit.
What is the difference between lean and Six Sigma?
Lean comes from the Toyota Production System. It works on time: waiting, extra steps, overproduction and stock. Six Sigma comes from Motorola. It works on variation and the defects it causes. Many problems need both, so many companies combine them as Lean Six Sigma.
Why check the gage before anything else?
Every measurement includes some error from the gage. If the gage adds a lot of spread, the control chart and the capability numbers describe the gage as much as the process. A Gage R&R result under 10% is good. Between 10% and 30% may be acceptable. Over 30% means fix the gage first.
Do I need a Six Sigma certification to use these tools?
No. Each tool can be learned and used on its own. Certifications such as green belt and black belt are training levels that some companies use to decide who leads projects.