Standardized work explained

Standardized work is the current best way to do a job, written down so every operator does it the same way. This guide builds one for a four-station cell.

Matt Savas · Reviewed October 2026 · About 6 minutes

What standardized work is

Standardized work (標準作業, hyōjun sagyō) is a written description of the safest and most reliable way known to do a job. It sets how often the job is done, the order of the steps and how many parts stay in the process. Toyota developed it as part of the Toyota Production System.

When every operator on every shift does the job the same way, the time per part is predictable. The standard is also the baseline for improvement. Without one, there is no way to tell whether a change made the job better.

The three elements

  • Takt time. How often the customer needs one part. It is the available working time divided by customer demand.
  • Work sequence. The order of steps the operator follows every cycle.
  • Standard in-process stock. The fewest parts that must be in the process for the operator to work through the cycle without waiting on a machine.

The forms

Three forms record the standard. Their times come from a time observation sheet.

  • Process capacity sheet. Lists each machine’s time per part, including run time and changeover, and the number of parts it can make in a shift.
  • Standardized work combination table. Plots the operator’s hand time, the machine time and the walking for one cycle on one timeline, with takt time as a line.
  • Standardized work chart. A drawing of the work area from above, with the walking path, the standard in-process stock and the quality and safety checks. Teams post it at the station.

A worked example

The cell below makes one part. The numbers are made up for this example. Scroll to build its standard one step at a time.

Standardized work for a four-station cell
The work chart on top, the combination table below.
Work chart: the cell from abovePressLoadLoad 7 sBenchDeburrDeburr 9 sGaugeInspectInspect 5 sChuteSetSet 4 s2 s2 s2 s2 sCombination table: one cycleLoadDeburrInspectSet0 s10 s20 s30 s40 sTakt 40 s7 s9 s5 s4 sPress 12 sCycle 33 s, takt 40 s, 7 s spare
1 of 6

The cell

One operator runs four stations in a loop: a press, a deburring bench, an inspection gauge and a chute for finished parts. The customer needs 1,380 parts a day.

2 of 6

Takt time

The cell works two 460-minute shifts, or 55,200 seconds a day. Takt time is 55,200 ÷ 1,380 = 40 seconds. The heavy line marks 40 seconds on the combination table.

3 of 6

Hand time

An observer times each element over several cycles and keeps the lowest time that repeats: load 7 seconds, deburr 9, inspect 5 and set 4. Each solid line is one element, in the order the operator does them.

4 of 6

Machine time

After loading, the press runs for 12 seconds on its own (dashed line). The operator walks on to the bench, so those seconds are not in the operator’s cycle. The process capacity sheet counts them: at 7 + 12 = 19 seconds a part, the press makes 1,452 parts a shift. The cell needs 690.

5 of 6

Walking

Each walk between stations takes 2 seconds, 8 seconds a cycle. The work chart draws the walks as the path around the cell. The combination table draws each one as a wavy line.

6 of 6

Cycle time against takt

Hand time plus walking is 25 + 8 = 33 seconds, 7 seconds under takt. Over takt, the team would move an element to another operator, shorten the walks or redesign the slowest element. The line balancing guide shows how.

Training and improvement

The forms describe the job. Operators learn it from a work instruction, which breaks each step into its key points and the reason for each one. For the press, one key point is to seat the part flat before clamping, because a tilted part jams the die. To write one, use the free TWI job instruction tool.

When the team finds a better method, they test it at the station. If it works, it goes into the forms and the work instruction, and the new standard is the baseline for the next change.

Common mistakes

  • Writing the standard in an office. Time the job at the station, with the operators who do it.
  • Using average times. An average includes the cycles where something went wrong. Use the lowest time that repeats, and treat the slow cycles as problems to solve.
  • Balancing operators before checking machines. If a machine cannot make enough parts in a shift, moving work between operators will not fix it. Fill in the process capacity sheet first.
  • Leaving the standard unchanged. When the layout, the method or takt time changes and the forms do not, operators stop following them.

How to start

Start with one cell and one operator. The free takt time calculator, time observation sheet and process capacity sheet cover the first steps. The combination table builder and work chart builder draw the two main forms, and the work instruction template covers training.

To read a combination table in more detail, see the combination table guide.

Frequently asked questions

What is standardized work?
Standardized work is the current best way known to do a job, written down so every operator does it the same way. It has three elements: takt time, the work sequence and standard in-process stock. Three forms record it: the process capacity sheet, the standardized work combination table and the standardized work chart.
What is the difference between takt time and cycle time?
Takt time comes from the customer. It is the available working time divided by demand, for example 55,200 seconds a day ÷ 1,380 parts = 40 seconds. Cycle time is how long the operator takes to do one cycle of the work, including walking. Standardized work fits the cycle time under takt time.
What is standard in-process stock?
It is the fewest parts that must be in the process for the operator to work through one cycle without waiting on a machine, counting the parts inside the machines. With too few, the operator waits for a machine to finish. With too many, extra parts sit between stations and hide problems such as defects. The count goes on the standardized work chart.
What is the difference between standardized work and a work instruction?
Standardized work describes the job as a whole: takt time, the order of the steps, the time for each and the parts kept in the process. A work instruction is for training. It breaks each step into its key points, such as a quality or safety check, and gives the reason for each one.