Yamazumi chart explained

A yamazumi chart is a stacked bar chart of the work on a line or cell, one bar per operator. Teams use it to balance the work to takt time, find the bottleneck and pick what to fix next.

Matt Savas · Reviewed October 2026 · About 7 minutes

What a yamazumi chart is

A yamazumi chart is a stacked bar chart of a line or a cell. Each bar is one operator or station. The bar is built by stacking that operator's work elements, the small steps that make up the job, one on top of the other. The height of the whole bar is that operator's cycle time.

A line across the chart marks takt time: how often the customer needs one unit. Every bar should end below that line. A bar above it means that operator can't keep up.

Yamazumi (山積み) is Japanese for “piled up,” because the work elements pile up like a stack. It is also called an operator balance chart. It is the main chart used in line balancing.

What a yamazumi chart does

A yamazumi chart helps a team do three things:

  • Balance the work to takt. It shows which stations are over takt and which have time to spare. Moving work elements between operators gets every bar under takt, so the work flows smoothly and the line meets customer demand.
  • Find the bottleneck. The tallest bar is the slowest station. The whole line can only go as fast as that station.
  • Pick what to fix. Each bar is split into work elements, and the waste is colored. In a kaizen, the team can see which elements to remove before moving anything.

Why the work needs balancing

On most lines the work is not balanced to takt. One operator can't finish in time and falls behind every cycle. The operator next to them finishes early and waits. A list of times makes this hard to see. The chart shows it in one picture, so the team can agree on what to fix first.

The slowest station sets the pace for the whole line. If it takes longer than takt time, the line makes fewer units than the customer needs, and the plant pays overtime to catch up.

A worked example

This example is one part of an electric car assembly line, with six people at stations 4 to 9. The numbers are made up. As you scroll, the chart builds one step at a time.

A yamazumi chart for six stations
Each step adds one piece to the chart.
Station 7, ten cycles, in seconds
Element12345678910LRT
Align drive unit6062586160636059616260
Torque 8 bolts4749484750474851494847
Fetch part2219241921231920252219
Connect HV cable3941404239384039414339
Check sensor2425262427242526242824
Reset tool and scan4255444260474250455842
Step 1 of 9

Time each work element

Start with station 7, the one that is always behind. List each work element the operator does. Then time each one ten times with a stopwatch. Time the real work, not the plan. The free time observation sheet does the math.

Station 7, ten cycles, in seconds
Element12345678910LRT
Align drive unit6062586160636059616260
Torque 8 bolts4749484750474851494847
Fetch part2219241921231920252219
Connect HV cable3941404239384039414339
Check sensor2425262427242526242824
Reset tool and scan4255444260474250455842
Step 2 of 9

Use the lowest repeatable time

For each element, use the lowest repeatable time (LRT): the lowest time that shows up more than once. Aligning the drive unit took 58 and 59 seconds once each and 60 seconds three times, so use 60. Don't use the average. Slow times, like the 55 and 60 for resetting the tool, come from problems: a part that won't fit, a missing part, a tool that sticks. An average hides those problems. Fix them instead.

050100150200
Align drive unitTorque 8 boltsFetch partConnect HV cableCheck sensorReset tool and scan
60s
47s
19s
39s
24s
42s
Station 7
231s
+21s
Takt 210s
Work element
800 ÷ 210 = 3.81, so at least 4 operators
Step 3 of 9

Stack the elements

Stack the six element times on top of each other in one bar. The height of the whole bar is the cycle time: 231 seconds for station 7.

050100150200
Align drive unitTorque 8 boltsFetch partConnect HV cableCheck sensorReset tool and scan
60s
47s
19s
39s
24s
17s
25s
Station 7
231s
+21s
Takt 210s
Value-added Needed, no value added Waste
800 ÷ 210 = 3.81, so at least 4 operators
Step 4 of 9

Color the work by value

Color each block by whether it changes the car. Dark blocks change it: aligning the drive unit, tightening the bolts, connecting the cable. Gray blocks don't change the car but are needed for now, like checking the sensor and scanning. Amber blocks are waste. At station 7, walking to the rack for a part takes 19 seconds. Waiting for the tool to reset takes 25 of the 42 seconds in the last element. That is 44 seconds of waste.

050100150200
Align drive unitTorque 8 boltsFetch partConnect HV cableCheck sensorReset tool and scan
60s
47s
19s
39s
24s
17s
25s
Station 7
231s
+21s
Takt 210s
Value-added Needed, no value added Waste
800 ÷ 210 = 3.81, so at least 4 operators
Step 5 of 9

Draw the takt line

Takt time is how often the customer needs one car. The line works 434 minutes a shift, which is 26,040 seconds, and the customer needs 124 cars. 26,040 ÷ 124 = 210, so the line must finish one car every 210 seconds. Draw a line at 210. Station 7 needs 231 seconds, 21 more than takt. That operator can't keep up, however hard they work.

050100150200
St 4
152s
+0s
St 5
188s
+0s
St 6
165s
+0s
St 7
231s
+21s
St 8
122s
+0s
St 9
122s
+0s
Takt 210s
Value-added Needed, no value added Waste
800 ÷ 210 = 3.81, so at least 4 operators
Step 6 of 9

Add every station

Now add a bar for each of the six stations. Station 7 is the only one over the line, so it is the bottleneck. Stations 8 and 9 need only 122 seconds each, so those operators wait 88 seconds every cycle. All six stations together hold 980 seconds of work, and 180 seconds of that is waste.

050100150200
St 4
124s
+0s
St 5
154s
+0s
St 6
137s
+0s
St 7
187s
+0s
St 8
100s
+0s
St 9
98s
+0s
Takt 210s
Value-added Needed, no value added
800 ÷ 210 = 3.81, so at least 4 operators
Step 7 of 9

Remove waste before you move work

It is tempting to move some of station 7's work to station 8. Take out the waste first. Otherwise you only move the waste to another station. Putting the parts rack next to station 7 ends the walk. Fixing the slow tool ends the wait. Across all six stations, 180 seconds of waste come out, and the work drops from 980 to 800 seconds. Every bar is now under the takt line, and nobody had to work faster.

050100150200
St 4
124s
+0s
St 5
154s
+0s
St 6
137s
+0s
St 7
187s
+0s
St 8
100s
+0s
St 9
98s
+0s
Takt 210s
Value-added Needed, no value added
800 ÷ 210 = 3.81, so at least 4 operators
Step 8 of 9

How many operators you need

Divide the total work by takt time and round up. 800 ÷ 210 = 3.81, so four people could do the work. Before the waste came out, it took five (980 ÷ 210 = 4.67). Six people work here today.

050100150200
Op A
189s
Op B
189s
Op C
189s
Op D
189s
Op E
44s
Next target
Takt 210s
Value-added Needed, no value added 90% of takt, 189s
800 ÷ 210 = 3.81, so at least 4 operators
Step 9 of 9

Rebalance the line

Now move work elements between operators. Give each person about 90% of takt, which is 189 seconds. That leaves a little time for small problems. Four people at 189 seconds cover 756 seconds of work. That leaves 44 seconds for a fifth person, which is not a full job. This is the next kaizen target: cut 44 more seconds from the zone, for example from the gray needed work, and four people can do it all.

Common mistakes

  • Averaging the times. The average includes the slow cycles where something went wrong. Use the lowest time that repeats, and fix the slow cycles.
  • Moving work before removing waste. If you move a walk to another station, someone still has to walk. Remove the waste first, then balance what is left.
  • Filling every job right up to takt. Every shift has jams and missing parts. A job with no spare time stops the line at the first problem. Aim for about 90% of takt.
  • Using planned times. Time the real work, with the people who do it.

How to start

Pick one area where someone is always behind. Time each work element ten times on the free time observation sheet. Then enter the lowest repeatable times in the free yamazumi chart builder, set your takt time, and move work elements until every bar fits under the line. The takt time guide shows how to work out takt.

Frequently asked questions

What is a yamazumi chart?
A stacked bar chart of a line or a cell. Each bar is one operator, built by stacking their work elements, and the height of the bar is their cycle time. A line marks takt time. Teams use it to balance the work to takt, find the bottleneck and choose which waste to remove.
What does yamazumi mean?
Yamazumi (山積み) is Japanese for "piled up." The blocks of work in each bar pile up like a stack.
How is it different from a cycle time bar chart?
A plain bar chart shows only each operator's total time. A yamazumi chart splits each bar into its work elements and colors them as value-added, needed, or waste. That shows which elements to remove and which can move to another operator.
How many operators do I need?
Add up all the work on the line, divide by takt time and round up. 800 seconds of work with a 210-second takt needs at least four people. Many lines have one or two more than that.
Why not load operators to 100% of takt?
Every shift has jams and missing parts. A job filled right up to takt has no spare time, so the first problem stops the line. About 90% of takt leaves time for small problems.